The then existing road between Hassanabadal and Abbottabad was deteriorated and became un-safe for traffic. NHA decided to carry out the feasibility study and improvement of this two lane road (70 km).
Services
Feasibility Study
Detailed Design
ECIL undertook following tasks for the above work at (1) & (2).
Road & structure condition survey
Engineering survey consisting of traverse survey, topographic survey, and cross section levelling
Traffic & axle load survey and traffic forecast
Road roughness survey
Benkelman beam deflection study
Hydrological investigations & study
Soil Investigations
Geotechnical & material investigations
Prepared preliminary design & preliminary cost estimates
Prepared economic feasibility which includes the derivation of Benefit Cost Ratio (BCR), Internal Rate of Return (IRR), Net Present Value (NPV) and ratio of project cost for the first year benefits of the project to demonstrate the economic and technical feasibility, including testing the results on HDM model
Feasibility report
Detailed engineering design of overlay & other improvement works, including bridges & structures
Tender documents & cost estimates
Detailed Construction Supervision Services
Detailed construction supervision of (70 km) road, including bridges/culverts
Contract management
Quality assurance
Checking & verifications of measurements